PMI-ACP · Question #637

An agile practitioner wants to ensure that stakeholders have current information about a project's progress. What should the agile practitioner do?

The correct answer is D. Post a project board in an area where all can view it. Posting a visible project board (e.g., Kanban or task board) is a foundational agile transparency practice known as an 'information radiator.' It provides real-time, passive visibility to all stakeholders without requiring scheduled meetings or manual document updates. Option A…

Submitted by eva_at· Apr 18, 2026Stakeholder Engagement

Question

An agile practitioner wants to ensure that stakeholders have current information about a project's progress. What should the agile practitioner do?

Options

  • ARegularly circulate an updated, detailed version of the project plan
  • BFrequently update the online project management office (PMO) repository site
  • CInvite the stakeholders to daily stand ups
  • DPost a project board in an area where all can view it

How the community answered

(36 responses)
  • A
    3% (1)
  • B
    6% (2)
  • C
    14% (5)
  • D
    78% (28)

Explanation

Posting a visible project board (e.g., Kanban or task board) is a foundational agile transparency practice known as an 'information radiator.' It provides real-time, passive visibility to all stakeholders without requiring scheduled meetings or manual document updates. Option A relies on a 'detailed project plan,' which is a waterfall artifact. Option B (updating a PMO repository) is less immediate and requires stakeholders to actively seek out information. Option C (inviting stakeholders to daily stand-ups) is disruptive to the team's focused ceremony and is not standard practice.

Topics

#Stakeholder Communication#Information Radiators#Project Transparency#Progress Visibility