PMI-ACP · Question #636
During a mature agile team's planning meeting, a team member proposes a new framework that would considerably reduce implementation time. However, the team lacks the confidence to try the new…
The correct answer is A. Develop a spike. A spike is a time-boxed, focused exploration or research task whose sole purpose is to reduce uncertainty and build team knowledge or confidence about a specific technology, approach, or problem. It is the ideal agile tool when a team wants to evaluate something new without…
Question
During a mature agile team's planning meeting, a team member proposes a new framework that would considerably reduce implementation time. However, the team lacks the confidence to try the new framework. To help the team gain confidence, what should the agile practitioner suggest?
Options
- ADevelop a spike
- BCreate an Ishikawa diagram
- CPerform a pre-mortem analysis
- DComplete a variance and trend analysis
How the community answered
(20 responses)- A70% (14)
- B5% (1)
- C15% (3)
- D10% (2)
Explanation
A spike is a time-boxed, focused exploration or research task whose sole purpose is to reduce uncertainty and build team knowledge or confidence about a specific technology, approach, or problem. It is the ideal agile tool when a team wants to evaluate something new without committing to full implementation. The spike produces knowledge - a concrete proof of concept - that replaces fear of the unknown with informed confidence. Option B (Ishikawa/fishbone diagram) is a root cause analysis tool, not applicable here. Option C (pre-mortem analysis) anticipates future failures but does not build hands-on technical confidence. Option D (variance and trend analysis) is a monitoring/forecasting technique unrelated to technology exploration.