The correct answer is B: Conduct story-mapping exercises to clarify deliverables and release priorities. Story mapping is a collaborative workshop technique where the team and stakeholders walk through user activities to build a shared understanding of the product's scope, priority, and phased delivery. It directly produces a visual alignment artifact that clarifies what will be del
Question
How can an agile team working on a new product ensure alignment with external stakeholders?
Options
- AAsk the product owner to provide a detailed product specification document
- BConduct story-mapping exercises to clarify deliverables and release priorities
- CHold a kick-off meeting to assign roles and responsibilities
- DWork with the scrum master and stakeholders to ensure agile principles are followed
Explanation
Story mapping is a collaborative workshop technique where the team and stakeholders walk through user activities to build a shared understanding of the product's scope, priority, and phased delivery. It directly produces a visual alignment artifact that clarifies what will be delivered and when—making it ideal for engaging external stakeholders. A detailed specification document (A) is a waterfall artifact. A kick-off meeting for roles (C) is a one-time event that doesn't address ongoing delivery alignment. Relying on the scrum master to enforce agile principles (D) doesn't address the stakeholder-alignment problem directly.