nerdexam
PMIPMI

PMI-ACP · Question #650

PMI-ACP Question #650: Real Exam Question with Answer & Explanation

The correct answer is C: Help the team choose one or two initiatives for immediate implementation. Agile retrospectives work best when they produce focused, actionable outcomes. Attempting to implement a long list of improvements simultaneously overwhelms the team and often results in none being completed effectively. The agile coach should facilitate prioritization so the tea

Submitted by helene.fr· Apr 18, 2026Continuous Improvement

Question

During a retrospective meeting, a team develops a large list of initiatives. All will have a positive impact and improve team performance. What should the agile coach do next?

Options

  • APositively acknowledge the list and share it with management
  • BImmediately have the team implement the initiatives
  • CHelp the team choose one or two initiatives for immediate implementation
  • DAsk the team to choose and implement the most complex initiative

Explanation

Agile retrospectives work best when they produce focused, actionable outcomes. Attempting to implement a long list of improvements simultaneously overwhelms the team and often results in none being completed effectively. The agile coach should facilitate prioritization so the team commits to one or two high-impact initiatives they can realistically complete before the next retrospective. Option A (sharing with management) defers action and misses the self-improvement opportunity. Option B risks team overload. Option D (most complex initiative) is the opposite of a sustainable, incremental improvement approach.

Topics

#Retrospective#Continuous Improvement#Agile Coach Role#Prioritization

Community Discussion

No community discussion yet for this question.

Full PMI-ACP PracticeBrowse All PMI-ACP Questions