PMI-ACP · Question #655

PMI-ACP Question #655: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-ACP to reveal the answer and full explanation for question #655. The question stem and answer options stay visible for context.

Submitted by jordan8· Apr 18, 2026Value-driven Delivery

Question

A product owner concludes that the majority of a project's value can be delivered by completing only the first half of the prioritized backlog. What should the product owner do next?

Options

  • ARemove the second half of the backlog, and communicate their decision in the next backlog
  • BReprioritize backlog items to future iterations
  • CWork with the team to deploy the first half of the backlog to ensure that value is realized
  • DMeet with project stakeholders to review the backlog and determine if the scope should be

Unlock PMI-ACP to see the answer

You've previewed enough free PMI-ACP questions. Unlock PMI-ACP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Value delivery#Product Owner role#Backlog prioritization#Early value realization