The correct answer is B: Ensure that they attend regular sprint meetings to provide product-feature feedback. In agile, the product owner is a core member of the Scrum team who participates in sprint ceremonies—sprint planning, sprint review, and retrospectives. The agile project leader's responsibility is to ensure the product owner attends these regular sprint meetings to give direct

Submitted by femi9· Apr 18, 2026Stakeholder Engagement

Question

How should an agile project leader interact with the product owner?

Options

  • AConduct regular one-on-one meetings to review development features and trace them back to the
  • BEnsure that they attend regular sprint meetings to provide product-feature feedback
  • CShare any new versions of the project plan with them, including updated statuses for tasks and
  • DSchedule meetings where they can provide team direction regarding new-feature priorities and

Explanation

In agile, the product owner is a core member of the Scrum team who participates in sprint ceremonies—sprint planning, sprint review, and retrospectives. The agile project leader's responsibility is to ensure the product owner attends these regular sprint meetings to give direct, timely feedback on developed features. One-on-one reviews (A) and sharing project plans (C) are more traditional PM behaviors. Scheduling separate direction meetings (D) is redundant since that direction is already given during sprint planning. The sprint cadence itself is the structured channel for product owner engagement.

Topics

#Product Owner#Agile ceremonies#Stakeholder communication#Feedback mechanisms

Community Discussion

No community discussion yet for this question.

Full PMI-ACP PracticeBrowse All PMI-ACP Questions