The correct answer is A: Refer to the values of the agile framework and the team. When team members disagree about a feature that delivers short-term business value but lacks a long-term solution, the right resolution path is to return to shared agile values and team agreements. Agile values - such as customer collaboration, sustainable development, and techni

Submitted by dimitri_ru· Apr 18, 2026Agile Principles and Mindset

Question

During sprint planning, team members have differing opinions on a feature that delivers business value but fails to provide a long-term solution for the customer. How should the team resolve this?

Options

  • ARefer to the values of the agile framework and the team
  • BReview the signed customer contract
  • CCheck the sprint priority list
  • DSubmit the problem to the product owner

Explanation

When team members disagree about a feature that delivers short-term business value but lacks a long-term solution, the right resolution path is to return to shared agile values and team agreements. Agile values - such as customer collaboration, sustainable development, and technical excellence - provide a common framework for navigating exactly these kinds of trade-off debates. It depersonalizes the disagreement and grounds it in principles the team has already committed to. Option B (signed contract) is a waterfall mindset and contrary to the agile value of customer collaboration over contract negotiation. Option C (sprint priority list) doesn't address the underlying values conflict. Option D (escalating to the product owner) is valid for prioritization decisions but not for resolving values-based team disagreements.

Topics

#Sprint Planning#Team Conflict#Agile Values#Decision Making