PMI-ACP · Question #676
PMI-ACP Question #676: Real Exam Question with Answer & Explanation
The correct answer is A: Refer to the values of the agile framework and the team. When team members disagree about a feature that delivers short-term business value but lacks a long-term solution, the right resolution path is to return to shared agile values and team agreements. Agile values - such as customer collaboration, sustainable development, and techni
Question
During sprint planning, team members have differing opinions on a feature that delivers business value but fails to provide a long-term solution for the customer. How should the team resolve this?
Options
- ARefer to the values of the agile framework and the team
- BReview the signed customer contract
- CCheck the sprint priority list
- DSubmit the problem to the product owner
Explanation
When team members disagree about a feature that delivers short-term business value but lacks a long-term solution, the right resolution path is to return to shared agile values and team agreements. Agile values - such as customer collaboration, sustainable development, and technical excellence - provide a common framework for navigating exactly these kinds of trade-off debates. It depersonalizes the disagreement and grounds it in principles the team has already committed to. Option B (signed contract) is a waterfall mindset and contrary to the agile value of customer collaboration over contract negotiation. Option C (sprint priority list) doesn't address the underlying values conflict. Option D (escalating to the product owner) is valid for prioritization decisions but not for resolving values-based team disagreements.