PMI-ACP · Question #665

When prioritizing features to be delivered in an iteration, on what features should an agile team defer work?

The correct answer is B. High-risk and low-value. Agile prioritization balances value and risk. Features that are high-risk AND low-value are the worst investment - they consume significant effort and attention while delivering little business benefit. These should be deferred (or potentially eliminated from the backlog…

Submitted by helene.fr· Apr 18, 2026Value-driven Delivery

Question

When prioritizing features to be delivered in an iteration, on what features should an agile team defer work?

Options

  • AHigh-risk and high-value
  • BHigh-risk and low-value
  • CLow-risk and low-value
  • DLow-risk and high-value

How the community answered

(26 responses)
  • A
    15% (4)
  • B
    77% (20)
  • C
    4% (1)
  • D
    4% (1)

Explanation

Agile prioritization balances value and risk. Features that are high-risk AND low-value are the worst investment - they consume significant effort and attention while delivering little business benefit. These should be deferred (or potentially eliminated from the backlog entirely). High-risk/high-value features (A) should be addressed early to de-risk the project. Low-risk/high-value features (D) are the easiest wins and should be completed soon. Low-risk/low-value features (C) can be deferred too, but they don't carry the dual burden of high risk, making high-risk/low-value the clear answer for deferral.

Topics

#Prioritization#Risk-value matrix#Value optimization#Feature selection

Community Discussion

No community discussion yet for this question.