- Question #201
A project is struggling because additional requirements keep being requested that prevent the team from focusing on the purpose of the project. This could have been avoided by usin...
- Question #202
A project is struggling because the sponsor continually has to increase funding which may cause the project to get cancelled. This could have been avoided by using:
- Question #203
During a conflict, which of the following resolution techniques describes forcing?
- Question #204
Which of the following conflict resolution techniques describes compromising?
- Question #205
Which of the following conflict resolution techniques describes avoiding?
- Question #206
Which of the following are included in regulatory compliance?
- Question #207
Which of the following are included in operational process compliance?
- Question #208
Which of the following is included in decision oversight?
- Question #209
Which of the following are included in phase gate approvals?
- Question #210
Which of the following is a component of a quality management plan that measures values of the output?
- Question #211
Which of the following components of a quality management plan ensures that the required quality is achieved?
- Question #212
Which of the following components of a quality management plan eliminates output that is not up to standards?
- Question #213
Which of the following components of a quality management plan is an initial quality measurement?
- Question #214
Which of the following steps oversees the productivity of the project team?
- Question #215
In QC testing, the project manager determines that the deliverable is outside of the specification limits. Which of the following processes allowed the project manager to make this...
- Question #216
Which of the following is a zero time activity?
- Question #217
Which of the following is the purpose of identifying stakeholders?
- Question #218
After completing a WBS, a project manager has been asked to identify human resource requirements. Which of the following should be included in the project plan?
- Question #219
Which of the following is also known as a fishbone diagram?
- Question #220
Which of the following is the budget amount needed to finish a project?
- Question #221
Which of the following can aid in the identification of root causes of defects?
- Question #222
Which of the following can aid in the identification of trends?
- Question #223
Which of the following can aid in the identification of the cause of the majority of the defects on a given project?
- Question #224
Which of the following would aid in the creation of a communication distribution plan?
- Question #225
Which of the following shows how often contracts would be closed for the procurements on a project?
- Question #226
Which of the following is an input into developing the project charter?
- Question #227
Which of the following describes an assumption?
- Question #228
Which of the following represents a good reason for formally closing out a project?
- Question #229
Which of the following describes the purpose of a war room on a project?
- Question #230
Which of the following represents a lead that is done in response to project compression?
- Question #231
The project team determined that using a multipoint estimate is more appropriate than single point estimate. Which of the following network diagram methods would be MOST appropriat...
- Question #232
Which of the following shows the interdependencies between activities on a project schedule?
- Question #233
Stakeholders have submitted change requests via email, telephone calls, stopping by, during meetings, and using the change request form. Also, once the change request is made, the...
- Question #234
Which of the following would use the WBS to aid in the creation of the cost estimate?
- Question #235
Which of the following can be identified using a run chart?
- Question #236
When performing quantitative risk analysis, which of the following should be produced?
- Question #237
Which of the following represents the purpose of performing qualitative risk analysis?
- Question #238
Which of the following individuals BEST represents the authority to authorize changes to the triple constraints?
- Question #239
In order to ensure higher commitment levels, estimates should be created, or approved by:
- Question #240
In month nine of a 12 month project, the customer approaches the project manager believing the project is at risk because 85% of the funds have been expended already. To give the c...
- Question #241
A project charter should allow the approver to easily identify which of the following?
- Question #242
For planning purposes, assumptions are:
- Question #243
The BEST time to communicate stakeholder expectations to the project team is:
- Question #244
The stakeholder has notified the project manager that new priorities have caused them to shift all of the business subject matter expert resources to a new project for one year. Th...
- Question #245
Which of the following statements is considered a project management best practice?
- Question #246
Given the schedule estimates of Best Case = 2 days, Worst Case = 12 days, and Most Likely = 4 days, calculate PERT.
- Question #247
A project manager has inherited a project that is $5 million over budget. Which of the following would the project manager do to help determine the root cause of the budget overrun...
- Question #248
During a project, which of the following shows when risks should be reassessed?
- Question #249
A project has 45 lines of communication. Which of the following shows how many stakeholders does the project have?
- Question #250
A status report shows that the earned value is $50,000, the planned value is $40,000, and actual costs are $45,000. Which of the following is the SPI of the project, and is the pro...