PK0-003 Exam Questions
500 real PK0-003 exam questions with expert-verified answers and explanations. Page 5 of 10.
- Question #201Project management concepts
A project is struggling because additional requirements keep being requested that prevent the team from focusing on the purpose of the project. This could have been avoided by usin...
scope creepscope managementscope statement - Question #202Project management concepts
A project is struggling because the sponsor continually has to increase funding which may cause the project to get cancelled. This could have been avoided by using:
change controlcost managementproject funding - Question #203Project management concepts
During a conflict, which of the following resolution techniques describes forcing?
conflict resolutionforcingproject teams - Question #204Project management concepts
Which of the following conflict resolution techniques describes compromising?
conflict resolutioncompromisingproject teams - Question #205Project management concepts
Which of the following conflict resolution techniques describes avoiding?
conflict resolutionavoidingproject teams - Question #206Basics of IT and governance
Which of the following are included in regulatory compliance?
regulatory compliancelawsgovernance - Question #207Basics of IT and governance
Which of the following are included in operational process compliance?
operational complianceaudit trailsversion controldata retention - Question #208Basics of IT and governance
Which of the following is included in decision oversight?
decision oversightchange control boardproject governance - Question #209Project life cycle phases
Which of the following are included in phase gate approvals?
phase gatesproject phaseslessons learnedbudget review - Question #210Project management concepts
Which of the following is a component of a quality management plan that measures values of the output?
quality managementquality metricsproject quality - Question #211Project management concepts
Which of the following components of a quality management plan ensures that the required quality is achieved?
quality managementquality assuranceproject quality - Question #212Project management concepts
Which of the following components of a quality management plan eliminates output that is not up to standards?
quality managementquality controlproject quality - Question #213Project management concepts
Which of the following components of a quality management plan is an initial quality measurement?
quality managementquality baselineproject quality - Question #214Project management concepts
Which of the following steps oversees the productivity of the project team?
work performanceproject monitoringteam productivity - Question #215Project management concepts
In QC testing, the project manager determines that the deliverable is outside of the specification limits. Which of the following processes allowed the project manager to make this...
quality controlvariance analysisspecification limitsproject monitoring - Question #216Project management concepts
Which of the following is a zero time activity?
milestoneproject schedulingproject activities - Question #217Project management concepts
Which of the following is the purpose of identifying stakeholders?
stakeholder identificationstakeholder managementproject stakeholders - Question #218Project management concepts
After completing a WBS, a project manager has been asked to identify human resource requirements. Which of the following should be included in the project plan?
human resource planningWBStraining needsproject plan - Question #219Tools and documentation
Which of the following is also known as a fishbone diagram?
fishbone diagramIshikawa diagramquality toolsroot cause analysis - Question #220Project management concepts
Which of the following is the budget amount needed to finish a project?
EVMETCcost managementbudget - Question #221Tools and documentation
Which of the following can aid in the identification of root causes of defects?
Ishikawa diagramsroot cause analysisquality control tools - Question #222Tools and documentation
Which of the following can aid in the identification of trends?
Run chartstrend analysisquality control tools - Question #223Tools and documentation
Which of the following can aid in the identification of the cause of the majority of the defects on a given project?
Pareto chartsdefect analysis80/20 rulequality control tools - Question #224Project management concepts
Which of the following would aid in the creation of a communication distribution plan?
Stakeholder registercommunication planningproject planning inputs - Question #225Project life cycle phases
Which of the following shows how often contracts would be closed for the procurements on a project?
Contract closureprocurement managementproject life cycle phases - Question #226Project life cycle phases
Which of the following is an input into developing the project charter?
Project charterbusiness caseproject initiationinputs and outputs - Question #227Project management concepts
Which of the following describes an assumption?
Assumptionsproject planningconstraints - Question #228Project life cycle phases
Which of the following represents a good reason for formally closing out a project?
Project closurelessons learnedhistorical informationorganizational process assets - Question #229Project management concepts
Which of the following describes the purpose of a war room on a project?
War roomcolocationproject environment - Question #230Project management concepts
Which of the following represents a lead that is done in response to project compression?
Project compressionfast trackingschedule managementcrashing - Question #231Tools and documentation
The project team determined that using a multipoint estimate is more appropriate than single point estimate. Which of the following network diagram methods would be MOST appropriat...
PERTmultipoint estimationschedule network analysisactivity duration estimation - Question #232Tools and documentation
Which of the following shows the interdependencies between activities on a project schedule?
Network diagramactivity dependenciesproject schedulescheduling tools - Question #233Tools and documentation
Stakeholders have submitted change requests via email, telephone calls, stopping by, during meetings, and using the change request form. Also, once the change request is made, the...
Process flow diagramchange controlstakeholder communicationprocess documentation - Question #234Project management concepts
Which of the following would use the WBS to aid in the creation of the cost estimate?
Bottom-up estimatingWBScost estimationscope management - Question #235Tools and documentation
Which of the following can be identified using a run chart?
Run chartstrend analysisquality control tools - Question #236Tools and documentation
When performing quantitative risk analysis, which of the following should be produced?
Quantitative risk analysisdecision tree analysisrisk management tools - Question #237Project management concepts
Which of the following represents the purpose of performing qualitative risk analysis?
Qualitative risk analysisrisk prioritizationrisk management processes - Question #238Project management concepts
Which of the following individuals BEST represents the authority to authorize changes to the triple constraints?
Project sponsorchange authoritytriple constraintproject governance - Question #239Project management concepts
In order to ensure higher commitment levels, estimates should be created, or approved by:
Estimation techniquesteam commitmentbottom-up estimation principlesresource management - Question #240Project management concepts
In month nine of a 12 month project, the customer approaches the project manager believing the project is at risk because 85% of the funds have been expended already. To give the c...
Cost Variance (CV)Earned Value Management (EVM)project performance monitoringcost management - Question #241Project management concepts
A project charter should allow the approver to easily identify which of the following?
project charterproject initiationproblem statement - Question #242Project management concepts
For planning purposes, assumptions are:
project planningassumptionsconstraints - Question #243Project management concepts
The BEST time to communicate stakeholder expectations to the project team is:
stakeholder communicationproject kick-off meetingexpectations management - Question #244Project life cycle phases
The stakeholder has notified the project manager that new priorities have caused them to shift all of the business subject matter expert resources to a new project for one year. Th...
project cancellationresource managementproject closure - Question #245Project life cycle phases
Which of the following statements is considered a project management best practice?
project life cycleprocess groupsproject initiation - Question #246Tools and documentation
Given the schedule estimates of Best Case = 2 days, Worst Case = 12 days, and Most Likely = 4 days, calculate PERT.
PERTschedule estimationproject scheduling - Question #247Project management concepts
A project manager has inherited a project that is $5 million over budget. Which of the following would the project manager do to help determine the root cause of the budget overrun...
budget overrunroot cause analysisscope management - Question #248Project life cycle phases
During a project, which of the following shows when risks should be reassessed?
risk managementrisk reassessmentproject life cycle - Question #249Tools and documentation
A project has 45 lines of communication. Which of the following shows how many stakeholders does the project have?
communication channelsstakeholder managementproject communication - Question #250Tools and documentation
A status report shows that the earned value is $50,000, the planned value is $40,000, and actual costs are $45,000. Which of the following is the SPI of the project, and is the pro...
earned value managementschedule performance indexproject metrics