nerdexam
CompTIA

PK0-003 · Question #238

Which of the following individuals BEST represents the authority to authorize changes to the triple constraints?

The correct answer is B. Sponsor. The project sponsor possesses the ultimate authority to authorize significant changes to a project's triple constraints (scope, time, and cost) because they are accountable for the project's overall success and alignment with business objectives.

Project management concepts

Question

Which of the following individuals BEST represents the authority to authorize changes to the triple constraints?

Options

  • AFunctional manager
  • BSponsor
  • CTeam member
  • DProject manager

How the community answered

(49 responses)
  • A
    2% (1)
  • B
    92% (45)
  • C
    4% (2)
  • D
    2% (1)

Why each option

The project sponsor possesses the ultimate authority to authorize significant changes to a project's triple constraints (scope, time, and cost) because they are accountable for the project's overall success and alignment with business objectives.

AFunctional manager

A functional manager oversees a specific department or function and lacks the broader project authority to approve changes to project-level triple constraints.

BSponsorCorrect

The project sponsor is the individual who champions the project, provides resources, and holds ultimate responsibility for its success, making them the appropriate authority to approve major changes to the project's foundational constraints. They typically own the project's business case and align it with organizational strategy.

CTeam member

A team member is responsible for executing tasks within the project and does not have the authority to make decisions regarding the project's overall constraints.

DProject manager

While a project manager manages changes, they usually do not have the sole authority to approve major changes to the triple constraints; such decisions often require sponsor approval due to their impact on the project's business case and organizational objectives.

Concept tested: Project sponsor authority over constraints

Topics

#Project sponsor#change authority#triple constraint#project governance

Community Discussion

No community discussion yet for this question.

Full PK0-003 Practice