Which of the following is an input into developing the project charter?

The correct answer is A. Business case. This question identifies a key input required before a project charter can be created.

Project life cycle phases

Question

Which of the following is an input into developing the project charter?

Options

  • ABusiness case
  • BProject scope statement
  • CRequirements documentation
  • DProject schedule

How the community answered

(29 responses)
  • A
    90% (26)
  • B
    3% (1)
  • D
    7% (2)

Why each option

This question identifies a key input required before a project charter can be created.

ABusiness caseCorrect

The business case defines the need for the project, its strategic alignment, and its justification, providing essential information to authorize the project and create the charter. It outlines the project's purpose and expected benefits, which are crucial for the charter.

BProject scope statement

The project scope statement is an output of the planning process, developed after the project charter authorizes the project.

CRequirements documentation

Requirements documentation is gathered during the planning phase, which occurs after the project charter has authorized the project.

DProject schedule

The project schedule is an output of the planning process, developed after the project charter has been created.

Concept tested: Project charter development inputs