PK0-003 · Question #226
Which of the following is an input into developing the project charter?
The correct answer is A. Business case. This question identifies a key input required before a project charter can be created.
Question
Which of the following is an input into developing the project charter?
Options
- ABusiness case
- BProject scope statement
- CRequirements documentation
- DProject schedule
How the community answered
(29 responses)- A90% (26)
- B3% (1)
- D7% (2)
Why each option
This question identifies a key input required before a project charter can be created.
The business case defines the need for the project, its strategic alignment, and its justification, providing essential information to authorize the project and create the charter. It outlines the project's purpose and expected benefits, which are crucial for the charter.
The project scope statement is an output of the planning process, developed after the project charter authorizes the project.
Requirements documentation is gathered during the planning phase, which occurs after the project charter has authorized the project.
The project schedule is an output of the planning process, developed after the project charter has been created.
Concept tested: Project charter development inputs