Which of the following describes an assumption?

The correct answer is C. Treated as true for the purpose of planning. This question asks for the definition of an assumption in project management.

Project management concepts

Question

Which of the following describes an assumption?

Options

  • ANot used on projects, because certainty is needed to proceed with planning
  • BAn unqualified estimate that can be firmed up later
  • CTreated as true for the purpose of planning
  • DA limitation that can impact the project that must be considered

How the community answered

(33 responses)
  • B
    3% (1)
  • C
    91% (30)
  • D
    6% (2)

Why each option

This question asks for the definition of an assumption in project management.

ANot used on projects, because certainty is needed to proceed with planning

Assumptions are fundamental to project planning, as complete certainty is rarely possible at the outset.

BAn unqualified estimate that can be firmed up later

An assumption is specifically something believed to be true, not just an unquantified estimate.

CTreated as true for the purpose of planningCorrect

An assumption is a factor that is considered to be true, real, or certain for planning purposes, even without proof or demonstration. Project planning often proceeds based on these assumed conditions until they can be verified or disproven.

DA limitation that can impact the project that must be considered

This describes a constraint, which is a restrictive condition, not an assumption.

Concept tested: Definition of a project assumption