PK0-003 · Question #212

Which of the following components of a quality management plan eliminates output that is not up to standards?

The correct answer is B. Quality control. Quality control is the component of a quality management plan responsible for identifying and eliminating outputs that fail to meet established quality standards.

Project management concepts

Question

Which of the following components of a quality management plan eliminates output that is not up to standards?

Options

  • AQuality assurance
  • BQuality control
  • CQuality baseline
  • DQuality metrics

How the community answered

(52 responses)
  • A
    2% (1)
  • B
    87% (45)
  • C
    8% (4)
  • D
    4% (2)

Why each option

Quality control is the component of a quality management plan responsible for identifying and eliminating outputs that fail to meet established quality standards.

AQuality assurance

Quality assurance focuses on ensuring the *processes* are correct to prevent defects, rather than directly eliminating non-standard output after it has been produced.

BQuality controlCorrect

Quality control (QC) is the process of monitoring specific project results to determine if they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory performance. This includes inspecting or testing deliverables and taking corrective action, such as rework or rejection, for any output that does not meet the specified quality criteria.

CQuality baseline

A quality baseline sets the *standards* against which quality is measured, but it does not perform the act of eliminating non-standard output.

DQuality metrics

Quality metrics are the specific data points used for measurement, not the process that eliminates non-standard output.

Concept tested: Quality management plan - quality control

Topics

#quality management#quality control#project quality