PK0-003 · Question #232

Which of the following shows the interdependencies between activities on a project schedule?

The correct answer is C. Network diagram. A network diagram is a visual representation of project activities and their logical sequence and dependencies, clearly illustrating how one activity's start or finish impacts others. This diagram is crucial for identifying the critical path and understanding project flow.

Tools and documentation

Question

Which of the following shows the interdependencies between activities on a project schedule?

Options

  • AMilestone chart
  • BPareto diagram
  • CNetwork diagram
  • DScatter diagram

How the community answered

(35 responses)
  • B
    6% (2)
  • C
    91% (32)
  • D
    3% (1)

Why each option

A network diagram is a visual representation of project activities and their logical sequence and dependencies, clearly illustrating how one activity's start or finish impacts others. This diagram is crucial for identifying the critical path and understanding project flow.

AMilestone chart

A milestone chart primarily shows key project milestones and their scheduled dates, but it does not detail the interdependencies between all activities.

BPareto diagram

A Pareto diagram is a bar chart used in quality control to prioritize problems or causes, not to display activity interdependencies.

CNetwork diagramCorrect

A network diagram visually represents the sequence in which project activities must be performed, showing their logical relationships and interdependencies. These diagrams are fundamental for scheduling, identifying the critical path, and understanding the flow of work within a project.

DScatter diagram

A scatter diagram is a graph that displays the relationship between two variables, typically used for correlation analysis, not for showing project activity interdependencies.

Concept tested: Project network diagram purpose

Source: https://www.pmi.org/learning/library/project-network-diagram-construction-6385

Topics

#Network diagram#activity dependencies#project schedule#scheduling tools