PK0-003 · Question #216
Which of the following is a zero time activity?
The correct answer is A. Milestone. A milestone represents a significant point or event in a project that marks a transition or completion, but it consumes no duration itself, making it a zero-time activity.
Question
Which of the following is a zero time activity?
Options
- AMilestone
- BCritical path
- CDeliverable
- DWork package
How the community answered
(45 responses)- A91% (41)
- B2% (1)
- C4% (2)
- D2% (1)
Why each option
A milestone represents a significant point or event in a project that marks a transition or completion, but it consumes no duration itself, making it a zero-time activity.
A milestone is a significant point or event in a project schedule, often used to mark the completion of a major phase, deliverable, or set of activities. By definition, a milestone has zero duration, as it represents an instantaneous point in time rather than an activity that consumes time.
The critical path is a sequence of activities that determines the shortest possible duration to complete the project, and its activities inherently have duration.
A deliverable is a tangible or intangible output of the project that results from activities, and the creation of a deliverable typically involves time-consuming work.
A work package is a small, manageable component of a project, consisting of defined work activities that consume time and resources to complete.
Concept tested: Project scheduling - milestone definition