In QC testing, the project manager determines that the deliverable is outside of the specification limits. Which of the following processes allowed the project manager to make this determination?

The correct answer is D. Identify variance. The process of identifying variance allows a project manager to determine when a deliverable's actual performance deviates from the established specification limits during quality control testing.

Project management concepts

Question

In QC testing, the project manager determines that the deliverable is outside of the specification limits. Which of the following processes allowed the project manager to make this determination?

Options

  • AReview change log
  • BRegression analysis
  • CMonitoring work performance
  • DIdentify variance

How the community answered

(52 responses)
  • A
    2% (1)
  • B
    4% (2)
  • C
    4% (2)
  • D
    90% (47)

Why each option

The process of identifying variance allows a project manager to determine when a deliverable's actual performance deviates from the established specification limits during quality control testing.

AReview change log

Reviewing the change log tracks approved or proposed changes to project components, not the direct comparison of a deliverable to its specifications for deviation.

BRegression analysis

Regression analysis is a statistical method used to estimate the relationships among variables, not a direct process for determining if a deliverable is outside specification limits in QC.

CMonitoring work performance

Monitoring work performance is an overarching process of tracking and reporting progress, while identifying variance is a specific technique or output within this process that makes the determination possible.

DIdentify varianceCorrect

Identifying variance involves comparing actual project performance or deliverable characteristics against the planned or baseline requirements and specification limits. When a deliverable falls outside these predefined limits during Quality Control (QC) testing, the project manager uses variance analysis to pinpoint this deviation.

Concept tested: Project quality control - variance analysis