PK0-003 · Question #214
Which of the following steps oversees the productivity of the project team?
The correct answer is D. Monitoring work performance. Monitoring work performance involves continuously tracking, reviewing, and reporting on project progress to ensure that project objectives are being met and to oversee team productivity.
Question
Which of the following steps oversees the productivity of the project team?
Options
- AAnalyze performance information
- BReview change log
- CIdentify variance
- DMonitoring work performance
How the community answered
(35 responses)- A3% (1)
- B6% (2)
- C3% (1)
- D89% (31)
Why each option
Monitoring work performance involves continuously tracking, reviewing, and reporting on project progress to ensure that project objectives are being met and to oversee team productivity.
Analyzing performance information is a specific activity within the monitoring process, typically done after data has been collected, rather than the overarching step of overseeing productivity.
Reviewing the change log focuses on tracking and managing changes to the project, not directly overseeing team productivity.
Identifying variance is a result of monitoring performance and comparing actuals to baselines, which is a specific analytical task, not the general oversight activity.
Monitoring work performance is a key project management process that continuously tracks, reviews, and reports the overall progress against the performance management plan. This ongoing oversight naturally includes observing and assessing the productivity of the project team to identify areas for improvement or necessary adjustments.
Concept tested: Project monitoring and control - team productivity oversight