PK0-003 · Question #248

During a project, which of the following shows when risks should be reassessed?

The correct answer is C. Throughout the project lifecycle. This question asks about the appropriate timing for reassessing project risks.

Project life cycle phases

Question

During a project, which of the following shows when risks should be reassessed?

Options

  • AA risk reassessment should occur at project closeout
  • BRisks should be reviewed during lessons learned
  • CThroughout the project lifecycle
  • DWhen a risk has become an issue and has to be acted upon

How the community answered

(56 responses)
  • A
    2% (1)
  • C
    95% (53)
  • D
    4% (2)

Why each option

This question asks about the appropriate timing for reassessing project risks.

AA risk reassessment should occur at project closeout

Waiting until project closeout for risk reassessment is too late, as active risk management is needed during execution.

BRisks should be reviewed during lessons learned

Reviewing risks during lessons learned is a retrospective activity, not part of ongoing, proactive risk reassessment during project execution.

CThroughout the project lifecycleCorrect

Risk reassessment is an ongoing, iterative process that must occur continuously throughout the entire project lifecycle to identify new risks, re-evaluate existing ones, and monitor mitigation effectiveness.

DWhen a risk has become an issue and has to be acted upon

Waiting until a risk becomes an issue is a reactive approach; effective risk management focuses on proactive identification and mitigation before risks materialize into issues.

Concept tested: Continuous risk monitoring and reassessment

Source: https://www.pmi.org/pmbok-guide-standards/pmbok

Topics

#risk management#risk reassessment#project life cycle