PK0-003 · Question #248
During a project, which of the following shows when risks should be reassessed?
The correct answer is C. Throughout the project lifecycle. This question asks about the appropriate timing for reassessing project risks.
Question
During a project, which of the following shows when risks should be reassessed?
Options
- AA risk reassessment should occur at project closeout
- BRisks should be reviewed during lessons learned
- CThroughout the project lifecycle
- DWhen a risk has become an issue and has to be acted upon
How the community answered
(56 responses)- A2% (1)
- C95% (53)
- D4% (2)
Why each option
This question asks about the appropriate timing for reassessing project risks.
Waiting until project closeout for risk reassessment is too late, as active risk management is needed during execution.
Reviewing risks during lessons learned is a retrospective activity, not part of ongoing, proactive risk reassessment during project execution.
Risk reassessment is an ongoing, iterative process that must occur continuously throughout the entire project lifecycle to identify new risks, re-evaluate existing ones, and monitor mitigation effectiveness.
Waiting until a risk becomes an issue is a reactive approach; effective risk management focuses on proactive identification and mitigation before risks materialize into issues.
Concept tested: Continuous risk monitoring and reassessment