PK0-003 · Question #246

Given the schedule estimates of Best Case = 2 days, Worst Case = 12 days, and Most Likely = 4 days, calculate PERT.

The correct answer is B. 5 days. This question requires calculating the Program Evaluation and Review Technique (PERT) expected duration using three-point estimates.

Tools and documentation

Question

Given the schedule estimates of Best Case = 2 days, Worst Case = 12 days, and Most Likely = 4 days, calculate PERT.

Options

  • A4 days
  • B5 days
  • C6 days
  • D8 days

How the community answered

(25 responses)
  • A
    8% (2)
  • B
    72% (18)
  • C
    4% (1)
  • D
    16% (4)

Why each option

This question requires calculating the Program Evaluation and Review Technique (PERT) expected duration using three-point estimates.

A4 days

4 days is the 'Most Likely' estimate, not the PERT calculated expected duration.

B5 daysCorrect

The PERT formula is (Optimistic + 4 * Most Likely + Pessimistic) / 6. Plugging in the values: (2 + 4*4 + 12) / 6 = (2 + 16 + 12) / 6 = 30 / 6 = 5 days.

C6 days

6 days is an incorrect calculation based on the PERT formula and given estimates.

D8 days

8 days is an incorrect calculation based on the PERT formula and given estimates.

Concept tested: PERT estimation calculation

Source: https://www.pmi.org/learning/library/pert-critical-path-scheduling-techniques-6997

Topics

#PERT#schedule estimation#project scheduling