nerdexam
CompTIA

PK0-003 · Question #250

A status report shows that the earned value is $50,000, the planned value is $40,000, and actual costs are $45,000. Which of the following is the SPI of the project, and is the project ahead or behind

The correct answer is D. SPI = 1.20, ahead of schedule. This question requires calculating the Schedule Performance Index (SPI) from given Earned Value (EV) and Planned Value (PV) figures, and then determining if the project is ahead of or behind schedule.

Tools and documentation

Question

A status report shows that the earned value is $50,000, the planned value is $40,000, and actual costs are $45,000. Which of the following is the SPI of the project, and is the project ahead or behind schedule?

Options

  • ASPI = 0.89, ahead of schedule
  • BSPI = 0.90, behind schedule
  • CSPI = 1.11, behind schedule
  • DSPI = 1.20, ahead of schedule

How the community answered

(32 responses)
  • A
    9% (3)
  • B
    6% (2)
  • C
    3% (1)
  • D
    81% (26)

Why each option

This question requires calculating the Schedule Performance Index (SPI) from given Earned Value (EV) and Planned Value (PV) figures, and then determining if the project is ahead of or behind schedule.

ASPI = 0.89, ahead of schedule

An SPI of 0.89 would indicate the project is behind schedule, not ahead, and the calculated SPI is not 0.89.

BSPI = 0.90, behind schedule

An SPI of 0.90 would indicate the project is behind schedule, not ahead, and the calculated SPI is not 0.90.

CSPI = 1.11, behind schedule

An SPI of 1.11 would indicate the project is ahead of schedule, not behind, and this numerical value is not provided as the correct answer's SPI.

DSPI = 1.20, ahead of scheduleCorrect

The Schedule Performance Index (SPI) is calculated by dividing the Earned Value (EV) by the Planned Value (PV). With an EV of $50,000 and a PV of $40,000, the calculated SPI is $50,000 / $40,000 = 1.25. An SPI value greater than 1.0 indicates that the project is performing better than planned and is ahead of schedule, which aligns with the 'ahead of schedule' status in option D.

Concept tested: Earned Value Management (EVM) SPI calculation

Topics

#earned value management#schedule performance index#project metrics

Community Discussion

No community discussion yet for this question.

Full PK0-003 Practice