CompTIA
PK0-003 · Question #251
PK0-003 Question #251: Real Exam Question with Answer & Explanation
The correct answer is B: Review the change control procedures for emergency changes. See the full explanation below for the reasoning.
Question
As part of the planning process, the change control board meets every other week. Immediately after the last change control meeting, a primary examiner called and indicated a new regulationwas passed and must be implemented within ten days. Which of the following should be done to ensure the change is implemented within the prescribed timeframe?
Options
- AIncorporate it as a task into the project plan and begin making the change
- BReview the change control procedures for emergency changes
- CWait for the next change control meeting and introduce it then
- DAsk the regulator for an extension of time
Community Discussion
No community discussion yet for this question.