For planning purposes, assumptions are:

The correct answer is B. considered true without demonstrated proof.. In project planning, assumptions are factors that are believed to be true, real, or certain without concrete proof, and they are used as a basis for decision-making and planning. These assumptions are crucial for proceeding with planning when certain information is unavailable or

Project management concepts

Question

For planning purposes, assumptions are:

Options

  • Aused to resolve constraints.
  • Bconsidered true without demonstrated proof.
  • Conly used during the initiation of a project.
  • Dresolved as the project is progressively elaborated.

How the community answered

(35 responses)
  • A
    6% (2)
  • B
    91% (32)
  • C
    3% (1)

Why each option

In project planning, assumptions are factors that are believed to be true, real, or certain without concrete proof, and they are used as a basis for decision-making and planning. These assumptions are crucial for proceeding with planning when certain information is unavailable or uncertain.

Aused to resolve constraints.

Assumptions are factors taken as true to allow planning to proceed, not directly used to resolve constraints, although they might influence how constraints are managed.

Bconsidered true without demonstrated proof.Correct

In project management, an assumption is a factor in the planning process that is considered to be true, real, or certain, without proof or demonstration. Project teams make assumptions when they do not have complete information, allowing them to proceed with planning based on what they believe will happen. These assumptions are documented and monitored, as their invalidation can impact the project.

Conly used during the initiation of a project.

Assumptions are used throughout the entire project lifecycle, not just during the initiation phase, as new assumptions can emerge or existing ones need to be re-evaluated during planning, execution, and monitoring.

Dresolved as the project is progressively elaborated.

Assumptions are not necessarily "resolved" as the project is elaborated; rather, they are validated, monitored, and updated as more information becomes available, and if proven false, they lead to replanning.

Concept tested: Definition and role of project assumptions

Topics