PK0-003 Practice Questions
501 real PK0-003 exam questions with expert-verified answers and explanations. Page 10 of 11.
- Question #451
It is important to complete a formal project closure process to: (Select Three).
- Question #452
Which of the following would be the benefit of saving a project binder in a centralized location?
- Question #453
In order to compare a current projects quality to that of a previously completed project, a project manager should use which of the following techniques?
- Question #454
A stakeholder has indicated that a three phase project must be completed in four months instead of the previously agreed upon six months. It is determined that fast-tracking the pr...
- Question #455
The EV of a particular project is $6 million. The CV is -$340,000. Which of the following can be determined from this information?
- Question #456
Which of the following processes incorporates the make-or-buy analysis?
- Question #457
The method of cost-estimating whereby the costs of the individual work packages are aggregated to form the full cost-estimate is called:
- Question #458
A project has a CPI of 0.6. Which of the following would BEST describe the cost-efficiency of the project?
- Question #459
In a highway project 5 miles (8 kilometers) out of the total 15 miles (24 kilometers) have been completed. The BAC is $900,000. Which of the following represents the ETC of this pr...
- Question #460
Which of the following are characteristics of a projects critical path? (Select Two).
- Question #461
A project sponsor has requested that weekly status updates are to be sent by email, detailing the schedule performance index (SPI) and schedule variance (SV) of the project. In whi...
- Question #462
A key team member is performing poorly on a project. The project manager has verified that the team member knows the project expectations. The project manager has met repeatedly wi...
- Question #463
Which of the following is the BEST way for an organization to obtain qualified vendors?
- Question #464
In order to complete the pre-project setup, which of the following is the MOST important task of the project sponsor?
- Question #465
Changing the project schedule to prevent a known risk is an example of which of the following risk responses?
- Question #466
Which of the following would be the MOST important objective of a kick-off meeting? (Select Two).
- Question #467
Three of the team members are having a conflict with each other. Which of the following steps should the project manager take to minimize the conflict?
- Question #468
A key stakeholder has asked the project manager to complete the project a week earlier than expected. To accomplish this objective, the project manager will have to ask the project...
- Question #469
A new project manager has been assigned to a high profile project. In order to determine project status, which of the following should the project manager do? (Select Two).
- Question #470
The project sponsor indicates that one of the key stakeholders is very unhappy with the project schedule. The other stakeholders are happy with the schedule. Which of the following...
- Question #471
Post-mortem analysis occurs in which of the following process groups?
- Question #472
In pre-project setup, which of the following must be completed prior to validating a project?
- Question #473
A project manager is presented with a change request for an ongoing project. Which of the following would be the FIRST action?
- Question #474
Communication preferences, cultural differences, and language barriers are BEST described as which of the following?
- Question #475
A healthcare company must store project records for seven years. This is an example of which of the following?
- Question #476
In order to obtain the best pricing and product quality, a project manager should:
- Question #477
Which of the following is created using the work breakdown structure (WBS) as an input?
- Question #478
A cause and effect diagram can also be called:
- Question #479
Which of the following is true of fast tracking a schedule?
- Question #480
A project team member is uncertain how many activities are required to complete a task. Which of the following documents should be referenced?
- Question #481
Which of the following is the BEST communication option for team building?
- Question #482
A project manager is informed that material expenditures will increase. Which of the following documents should be referenced to address this increase?
- Question #483
The project charter is an output of which of the following project phases?
- Question #484
All of the following are considered part of the risk management plan EXCEPT the risk:
- Question #485
Control limits would be found in which of the following plans?
- Question #486
Which of the following are process groups in the project life cycle? (Select Three).
- Question #487
A project team is comfortable working as a group and has accepted all the project ground rules. They support each other to reach the project goals. Which of the following stages of...
- Question #488
Which of the following would a project manager organize and implement in order to provide decision oversight to scope changes?
- Question #489
Which of the following contract types places the LEAST amount of risk on the seller?
- Question #490
Which of the following is created as part of the closing phase?
- Question #491
Several stakeholders have asked the project manager to provide a weekly performance report. Which of the following may be the reason for the request?
- Question #492
A key stakeholder sends an email to the project manager expressing dissatisfaction with the progress of the project. Which of the following would be the BEST way for the project ma...
- Question #493
Which of the following would be the MOST effective way for a project manager to create a budget estimate?
- Question #494
A project manager has been asked to create an issues log. Which of the following should be included in the issues log? (Select TWO).
- Question #495
In order to satisfy a difficult stakeholder, a project manager has asked the project team to include more services than were outlined in the statement of work (SOW). Which of the f...
- Question #496
The team members have notified the project manager of several risks which may have a significant impact upon the project. Which of the following should the project manager do FIRST...
- Question #497
Which of the following options is the BEST reason for a project manager to develop a version control standard?
- Question #498
Which of the following would be used to cover the cost of an identified risk?
- Question #499
A Pareto diagram focuses attention on which of the following?
- Question #500
Which of the following BEST identifies the correct number of layers in a WBS?