PK0-003 · Question #464
In order to complete the pre-project setup, which of the following is the MOST important task of the project sponsor?
The correct answer is A. Obtain funding for the project.. The question asks to identify the most critical pre-project responsibility of a project sponsor.
Question
In order to complete the pre-project setup, which of the following is the MOST important task of the project sponsor?
Options
- AObtain funding for the project.
- BProvide quality review of the deliverables.
- CProvide leadership to the project team.
- DObtain resolution of the application development issues.
How the community answered
(21 responses)- A95% (20)
- C5% (1)
Why each option
The question asks to identify the most critical pre-project responsibility of a project sponsor.
During the pre-project setup phase, the project sponsor's most critical task is to secure the necessary funding. Without adequate financial resources, the project cannot officially begin or proceed to subsequent planning and execution stages.
Providing quality review of deliverables is typically an ongoing task during project execution and closure, not the most important pre-project setup task.
While providing leadership is an ongoing role of a project sponsor throughout the project lifecycle, securing funding is a more foundational pre-project task necessary for the project's very initiation.
Obtaining resolution of application development issues is a task relevant to project execution for IT projects, not a primary pre-project setup task for the sponsor.
Concept tested: Project Sponsor Role - Pre-project Responsibilities
Source: https://www.pmi.org/learning/library/project-sponsor-key-role-value-add-6428
Topics
Community Discussion
No community discussion yet for this question.