Changing the project schedule to prevent a known risk is an example of which of the following risk responses?

The correct answer is B. Avoidance. Changing a project schedule to eliminate a known risk before it occurs is a proactive strategy known as risk avoidance.

Project management concepts

Question

Changing the project schedule to prevent a known risk is an example of which of the following risk responses?

Options

  • AMitigation
  • BAvoidance
  • CAcceptance
  • DTransference

How the community answered

(36 responses)
  • B
    92% (33)
  • C
    3% (1)
  • D
    6% (2)

Why each option

Changing a project schedule to eliminate a known risk before it occurs is a proactive strategy known as risk avoidance.

AMitigation

Mitigation reduces the probability or impact of a risk, but does not eliminate it.

BAvoidanceCorrect

Risk avoidance involves eliminating the threat or protecting the project from its impact by changing the project plan to prevent the risk event from happening altogether. Changing the schedule to prevent a known risk is a direct action to avoid the risk.

CAcceptance

Acceptance involves deciding not to take any action to address the risk, either passively or actively.

DTransference

Transference shifts the responsibility for the risk and its impact to a third party.

Concept tested: Project risk response strategies - avoidance

Topics

#Risk management#Risk avoidance#Risk response strategies