PK0-003 · Question #453
In order to compare a current projects quality to that of a previously completed project, a project manager should use which of the following techniques?
The correct answer is C. Benchmarking. Benchmarking is the technique used to compare a current project's quality, performance, or practices against those of previously completed projects or external organizations. It helps identify best practices and areas for improvement.
Question
In order to compare a current projects quality to that of a previously completed project, a project manager should use which of the following techniques?
Options
- AProcess improvement
- BQuality metrics
- CBenchmarking
- DCost-benefit analysis
How the community answered
(46 responses)- A4% (2)
- B7% (3)
- C87% (40)
- D2% (1)
Why each option
Benchmarking is the technique used to compare a current project's quality, performance, or practices against those of previously completed projects or external organizations. It helps identify best practices and areas for improvement.
Process improvement focuses on optimizing the methods and procedures within a project rather than comparing the project's overall quality against others.
Quality metrics are specific measures used to track quality attributes, but they are tools used within a comparison rather than the comparison technique itself.
Benchmarking involves comparing the performance or practices of a project to those of other projects, either internal or external, to identify best practices, measure performance, and find ways to improve. When a project manager needs to compare a current project's quality against previously completed projects, benchmarking provides the necessary comparative analysis.
Cost-benefit analysis is a technique used to evaluate the financial feasibility of a project or a decision by comparing the costs of an action against its benefits.
Concept tested: Project quality management - Benchmarking