Which of the following would a project manager organize and implement in order to provide decision oversight to scope changes?

The correct answer is C. Change control board. A Change Control Board (CCB) is the formal body established to review, evaluate, approve, or reject proposed changes to project baselines, including scope.

Project management concepts

Question

Which of the following would a project manager organize and implement in order to provide decision oversight to scope changes?

Options

  • ARequest for Proposal (RFP)
  • BQuality management plan
  • CChange control board
  • DVersion control system

How the community answered

(24 responses)
  • A
    8% (2)
  • C
    88% (21)
  • D
    4% (1)

Why each option

A Change Control Board (CCB) is the formal body established to review, evaluate, approve, or reject proposed changes to project baselines, including scope.

ARequest for Proposal (RFP)

A Request for Proposal (RFP) is a document used in procurement to solicit proposals from potential sellers, not for managing internal project scope changes.

BQuality management plan

The quality management plan outlines how project quality will be managed and controlled, but it does not provide the decision-making authority for scope changes.

CChange control boardCorrect

A Change Control Board (CCB) is a formally constituted group that is responsible for reviewing, evaluating, approving, delaying, or rejecting changes to a project and recording such decisions, providing essential oversight for scope modifications.

DVersion control system

A version control system manages different iterations of documents and code, providing a historical record but not the formal decision-making body for approving scope changes.

Concept tested: Project Change Management and Change Control Board

Topics

#change control board#scope change management#project governance