PK0-003 · Question #487
A project team is comfortable working as a group and has accepted all the project ground rules. They support each other to reach the project goals. Which of the following stages of team development is
The correct answer is B. Performing. The team's behavior of working comfortably, accepting ground rules, and mutually supporting goals aligns with the characteristics of the Performing stage of team development.
Question
A project team is comfortable working as a group and has accepted all the project ground rules. They support each other to reach the project goals. Which of the following stages of team development is the project team demonstrating?
Options
- AStorming
- BPerforming
- CConforming
- DForming
How the community answered
(23 responses)- B87% (20)
- C4% (1)
- D9% (2)
Why each option
The team's behavior of working comfortably, accepting ground rules, and mutually supporting goals aligns with the characteristics of the Performing stage of team development.
Storming is characterized by conflict, resistance to project requirements, and disagreements among team members as they vie for roles and influence.
In the Performing stage, the team functions as a highly cohesive unit, focused on achieving the project's goals with strong interdependence, mutual support, and effective problem-solving after resolving initial conflicts.
Conforming is not a recognized stage in Tuckman's model of team development.
Forming is the initial stage where team members are polite, often reserved, and getting to know each other, typically still unsure of their roles and responsibilities.
Concept tested: Tuckman's Stages of Team Development