PK0-003 · Question #486
Which of the following are process groups in the project life cycle? (Select Three).
The correct answer is D. Initiating E. Closing F. Planning. The Project Management Institute (PMI) defines five core process groups in the project life cycle: Initiating, Planning, Executing, Monitoring and Controlling, and Closing.
Question
Which of the following are process groups in the project life cycle? (Select Three).
Options
- AAccepting
- BMitigating
- CAvoiding
- DInitiating
- EClosing
- FPlanning
How the community answered
(49 responses)- A4% (2)
- B2% (1)
- C2% (1)
- D92% (45)
Why each option
The Project Management Institute (PMI) defines five core process groups in the project life cycle: Initiating, Planning, Executing, Monitoring and Controlling, and Closing.
Accepting is typically a concept related to stakeholder acceptance or a risk response strategy, not a primary project management process group.
Mitigating is a risk response strategy aimed at reducing the probability or impact of a threat, not a distinct project management process group.
Avoiding is a risk response strategy that eliminates the threat or condition causing it, not a core project management process group.
Initiating is a project management process group focused on defining and authorizing the project or a phase of the project.
Closing is a project management process group responsible for formally completing the project, phase, or contract.
Planning is a project management process group that establishes the scope, refines objectives, and defines the course of action required to achieve the project objectives.
Concept tested: Project Management Process Groups