PK0-003 · Question #486

Which of the following are process groups in the project life cycle? (Select Three).

The correct answer is D. Initiating E. Closing F. Planning. The Project Management Institute (PMI) defines five core process groups in the project life cycle: Initiating, Planning, Executing, Monitoring and Controlling, and Closing.

Project life cycle phases

Question

Which of the following are process groups in the project life cycle? (Select Three).

Options

  • AAccepting
  • BMitigating
  • CAvoiding
  • DInitiating
  • EClosing
  • FPlanning

How the community answered

(49 responses)
  • A
    4% (2)
  • B
    2% (1)
  • C
    2% (1)
  • D
    92% (45)

Why each option

The Project Management Institute (PMI) defines five core process groups in the project life cycle: Initiating, Planning, Executing, Monitoring and Controlling, and Closing.

AAccepting

Accepting is typically a concept related to stakeholder acceptance or a risk response strategy, not a primary project management process group.

BMitigating

Mitigating is a risk response strategy aimed at reducing the probability or impact of a threat, not a distinct project management process group.

CAvoiding

Avoiding is a risk response strategy that eliminates the threat or condition causing it, not a core project management process group.

DInitiatingCorrect

Initiating is a project management process group focused on defining and authorizing the project or a phase of the project.

EClosingCorrect

Closing is a project management process group responsible for formally completing the project, phase, or contract.

FPlanningCorrect

Planning is a project management process group that establishes the scope, refines objectives, and defines the course of action required to achieve the project objectives.

Concept tested: Project Management Process Groups

Topics

#project process groups#project life cycle#initiating#planning#closing