Control limits would be found in which of the following plans?
The correct answer is B. Quality management plan. Control limits are statistical thresholds used to monitor and control process stability, and their definition is a core component of how project quality is managed.
Question
Control limits would be found in which of the following plans?
Options
- AProcurement management plan
- BQuality management plan
- CChange management plan
- DScope management plan
How the community answered
(38 responses)- A5% (2)
- B89% (34)
- C3% (1)
- D3% (1)
Why each option
Control limits are statistical thresholds used to monitor and control process stability, and their definition is a core component of how project quality is managed.
The procurement management plan focuses on acquiring products, services, or results from outside the project team, not on internal process control limits.
The Quality Management Plan describes how quality policies will be implemented, including the specific metrics, tools, and techniques like control limits used for statistical process control to monitor and ensure quality performance.
The change management plan outlines the process for managing and controlling changes to project baselines, not for defining quality control thresholds.
The scope management plan details how the project and product scope will be defined, validated, and controlled, without specifying quality control limits.
Concept tested: Project Quality Management Plan components