Question
Which of the following are characteristics of a projects critical path? (Select Two).
Options
- AThe critical path is the longest duration.
- BThe critical path has the least amount of resources.
- CThe critical path is the shortest duration.
- DThe critical path has less than or equal to zero float time.
- EThe critical path has a greater than zero float time.