PK0-003 · Question #459

In a highway project 5 miles (8 kilometers) out of the total 15 miles (24 kilometers) have been completed. The BAC is $900,000. Which of the following represents the ETC of this project?

The correct answer is D. $600,000. Given 5 miles completed out of 15 total and a Budget At Completion (BAC) of $900,000, the Estimate To Complete (ETC) for the remaining work is calculated to be $600,000.

Project management concepts

Question

In a highway project 5 miles (8 kilometers) out of the total 15 miles (24 kilometers) have been completed. The BAC is $900,000. Which of the following represents the ETC of this project?

Options

  • A$150,000
  • B$300,000
  • C$450,000
  • D$600,000

How the community answered

(44 responses)
  • A
    14% (6)
  • B
    7% (3)
  • C
    5% (2)
  • D
    75% (33)

Why each option

Given 5 miles completed out of 15 total and a Budget At Completion (BAC) of $900,000, the Estimate To Complete (ETC) for the remaining work is calculated to be $600,000.

A$150,000

This value does not correctly represent the cost of the remaining two-thirds of the work based on the total budget.

B$300,000

This value represents one-third of the total budget, which would be the cost of the completed work, not the remaining work.

C$450,000

This value represents half of the total budget, not the cost of the remaining two-thirds of the work.

D$600,000Correct

To determine the Estimate To Complete (ETC), we first calculate the proportion of work remaining. With 5 miles completed out of 15, there are 10 miles remaining (15 - 5 = 10). Assuming future work will be completed at the budgeted rate, the ETC is calculated as (Remaining Work / Total Work) * Budget At Completion (BAC), which is (10/15) * $900,000 = (2/3) * $900,000 = $600,000.

Concept tested: Earned Value Management - Estimate To Complete (ETC)

Topics

#earned value management#ETC#estimate to complete#cost forecasting