Question
In a highway project 5 miles (8 kilometers) out of the total 15 miles (24 kilometers) have been completed. The BAC is $900,000. Which of the following represents the ETC of this project?
Options
- A$150,000
- B$300,000
- C$450,000
- D$600,000
Unlock PK0-003 to see the answer