nerdexam
CompTIA

PK0-003 · Question #479

Which of the following is true of fast tracking a schedule?

The correct answer is B. Project activities will be performed concurrently.. Fast tracking is a schedule compression technique used in project management to shorten the project duration by performing activities in parallel that would typically be done sequentially.

Project management concepts

Question

Which of the following is true of fast tracking a schedule?

Options

  • AProject schedule critical path will change.
  • BProject activities will be performed concurrently.
  • CProject schedule is shortened by decreasing the project scope.
  • DProject schedule lead times are increased.

How the community answered

(28 responses)
  • A
    4% (1)
  • B
    93% (26)
  • C
    4% (1)

Why each option

Fast tracking is a schedule compression technique used in project management to shorten the project duration by performing activities in parallel that would typically be done sequentially.

AProject schedule critical path will change.

While fast tracking can potentially change the critical path, this is a possible outcome or consequence, not the defining truth of what fast tracking is.

BProject activities will be performed concurrently.Correct

Fast tracking involves taking activities that were planned to be performed in sequence and scheduling them to occur concurrently, or with some overlap. This overlap can reduce the overall project duration, though it often increases project risk due to the potential for rework or quality issues.

CProject schedule is shortened by decreasing the project scope.

Shortening the project schedule by decreasing the project scope is scope reduction, not the fast tracking technique.

DProject schedule lead times are increased.

Fast tracking aims to reduce the total project duration by overlapping activities, which often involves shortening lead times, not increasing them.

Concept tested: Project schedule compression - fast tracking

Source: https://www.pmi.org/blog/what-is-project-schedule-compression

Topics

#Schedule compression#Fast tracking#Project scheduling#Critical path

Community Discussion

No community discussion yet for this question.

Full PK0-003 Practice