CompTIA
PK0-003 · Question #468
PK0-003 Question #468: Real Exam Question with Answer & Explanation
Sign in or unlock PK0-003 to reveal the answer and full explanation for question #468. The question stem and answer options stay visible for context.
Question
A key stakeholder has asked the project manager to complete the project a week earlier than expected. To accomplish this objective, the project manager will have to ask the project team to work overtime, which will increase the cost of the project. Which of the following should be the NEXT step?
Options
- AAsk the key stakeholder for more funding for the project.
- BAsk the project team to work overtime to finish the project.
- CObtain an approved change control document before changing the project schedule.
- DAgree to complete the project using the new schedule.
Unlock PK0-003 to see the answer
You've previewed enough free PK0-003 questions. Unlock PK0-003 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.