PK0-003 · Question #483

The project charter is an output of which of the following project phases?

The correct answer is A. Initiation. The project charter is formally authorized and issued during the Initiation phase, marking the official start of a project or phase.

Project life cycle phases

Question

The project charter is an output of which of the following project phases?

Options

  • AInitiation
  • BPlanning
  • CExecution
  • DClosing

How the community answered

(28 responses)
  • A
    93% (26)
  • B
    4% (1)
  • D
    4% (1)

Why each option

The project charter is formally authorized and issued during the Initiation phase, marking the official start of a project or phase.

AInitiationCorrect

The Initiation phase is where the project or a phase officially begins, and the project charter is the foundational document created in this phase to formally authorize the project and grant the project manager authority. It establishes the project's purpose, objectives, and high-level requirements.

BPlanning

The Planning phase follows initiation and focuses on detailing the project's scope, schedule, and budget, not creating the initial charter.

CExecution

The Execution phase involves carrying out the work defined in the project plan, which occurs after the charter has been established.

DClosing

The Closing phase involves formalizing project completion and releasing resources, long after the project charter has been issued.

Concept tested: Project charter creation phase

Topics

#project charter#project initiation#project phases

Community Discussion

No community discussion yet for this question.