C_TSCM42_65 Exam Questions
158 real C_TSCM42_65 exam questions with expert-verified answers and explanations. Page 2 of 4.
- Question #55
What repetitive manufacturing options can you use to carry out line loading in the SAP ECC system and thus generate Run Schedule Quantities (RSQ) from normal planned orders? (Choos...
- Question #56
Which data forms the basis for calculating the capacity requirement for an operation? (Choose three.)
- Question #57
Which of the following activities within the KANBAN procedure normally triggers subsequent stock posting of the goods receipt?
- Question #58
Which of the following elements do you have to prepare for costing of a production order to function without errors? (Choose three.)
- Question #59
In which of the following objects can you activate backflushing of components if you want to use this functionality during order confirmation? (Choose three.)
- Question #60
Which of the following master data do you need to provide for process manufacturing? (Choose three.)
- Question #61
In your company planning strategies are used in the SAP-ECC demand management that is based on consumption. Which of the following statements about consumption is true? (Choose two...
- Question #62
In production order processing, for which of the following objects can you enter a confirmation? (Choose three.)
- Question #63
Which types of objects can be changed with Engineering Change Management? (Choose three.)
- Question #64
When analyzing the SAP ECC order report for a planned order for a finished product, you discover that one of the assemblies will not be available in time for the scheduled final as...
- Question #65
Which of the following statements about the SAP Solution Manager listed is correct?
- Question #67
In what order are the individual steps of material requirements planning performed in SAP ECC?
- Question #69
In the course of a customer project, you are confronted with an SAP ECC system that shows the error message displayed below when you test requirements planning in plant 1000. Large...
- Question #70
What does SAP ERP mean?
- Question #71
Which of the following statements is true for the simulation mode in the context of material requirements planning in SAP ECC?
- Question #72
Which of the following features are offered by MRP Areas (Material Requirements Planning Areas)? (Choose two.)
- Question #73
A supply chain planning run is to be carried out in the SAP ECC system as an example. What would be the most effective sequence in which to run through the planning modules?
- Question #74
An enterprise wants to use SAP ECC requirements planning together with the NETPL procedure (net change planning in the planning horizon). The planning horizon is to be set equally...
- Question #75
Which of the following efforts can be minimized using the KANBAN procedure?
- Question #76
In the SAP ECC system, a material is produced with the help of production orders. Though originally used for rate-based planning only, the planning table is to be used to plan this...
- Question #77
Which functions lead to a reduction in the capacity requirement for an individual operation at a work center? (Choose three.)
- Question #78
With which functions of the process order can you fulfill the requirements of the Good Manufacturing Practices (GMP) standard? (Choose three.)
- Question #79
The company you advise wants to control the availability check in so that when a production and/or process order is created, the following receipts or issues are taken into account...
- Question #80
Which of the following statements is true for the ATP (available to promise) availability check in SAP ECC that is triggered from a customer order?
- Question #82
Which statements are true for ECC Long-Term Planning (LTP)? (Choose two.)
- Question #83
Which production order function can no longer be carried out after the order is released?
- Question #84
Which of the following activities is necessary for the capacity availability check to be carried out automatically when a production order is released?
- Question #85
A project team member analyzes the following situation in SAP ECC in the stock/requirements list for a finished product: there is only one customer order and one fixed planned orde...
- Question #86
What features related to process orders can be used to fulfill Good Manufacturing Practices (GMP) requirements? (Choose three)
- Question #87
Which of the following statements about consumption are correct? (Choose two)
- Question #88
Where can you define the valid receivers for production order costs?
- Question #89
When analyzing the SAP ECC order report for a planned order for a finished product, you discover that one of the assemblies will not be available in time for the scheduled final as...
- Question #90
What does SAP ERP mean?
- Question #91
Which functions can be triggered before releasing a production order? (Choose three)
- Question #92
What is a feature of the simu-lation mode for material requirements planning in SAP ECC?
- Question #93
Which of the following functions does SAP Supply Chain Management (SCM) offer?
- Question #94
What sequence do you follow in master data maintenance to define the production of a material?
- Question #95
In what sequence are the steps of material requirements planning performed in SAP ECC?
- Question #96
In SAP ECC, you calculate the standard available capacity for a work center capacity using the following data: - Start: 7:00:00 a.m. - End: 3:00:00 p.m. - Break duration: 1 hour -...
- Question #97
For which of the following objects can you enter a confirmation? (Choose two)
- Question #98
When modeling in-house production using SAP ECC, on which business levels can you create a bill of material (BOM)? (Choose two)
- Question #99
What could be a consequence of the confirmation of an operation?
- Question #100
In which master data object do you set the standard values for an operation?
- Question #101
You maintained the planning strategy group 10 (make-to-stock production) in the material master (SAP ECC) of a material. For the coming months you have planned requirements with re...
- Question #102
Which activity can trigger an automatic availability check for the components of a production order?
- Question #103
In the SAP ECC system, a material is produced using production orders. The planning table of repetitive manufacturing should be used to plan line loading for this material. On the...
- Question #104
Which objects can affect the calculation of capacity requirements for an operation? (Choose three)
- Question #105
Your customer tests the firming options for planned orders in SAP ECC using a test material. Therefore, the customer sets a firming date in the stock/requirements list manually. Ad...
- Question #106
When testing requirements planning in plant 1000, you receive the error message displayed below. Large numbers of materials are already available in plant 1000. As a first step in...
- Question #107
What are characteristics of repetitive manufacturing? (Choose three)