nerdexam
SAP

C_TSCM42_65 · Question #72

Which of the following features are offered by MRP Areas (Material Requirements Planning Areas)? (Choose two.)

The correct answer is A. An MRP Area may include different storage locations. B. Subcontracting is supported by MRP Areas. See the full explanation below for the reasoning.

Question

Which of the following features are offered by MRP Areas (Material Requirements Planning Areas)? (Choose two.)

Options

  • AAn MRP Area may include different storage locations.
  • BSubcontracting is supported by MRP Areas.
  • CA storage location may be assigned to different MRP Areas.
  • DMake-to-order production is supported by storage location MRP Areas.

How the community answered

(30 responses)
  • A
    77% (23)
  • C
    10% (3)
  • D
    13% (4)

Community Discussion

No community discussion yet for this question.

Full C_TSCM42_65 Practice