From what point can you no longer use the Read PP master data in the production order?

The correct answer is B. After the first posting of goods movements or confirmation. See the full explanation below for the reasoning.

Question

From what point can you no longer use the Read PP master data in the production order?

Options

  • AAfter printing the order papers.
  • BAfter the first posting of goods movements or confirmation.
  • CFrom the release of the production order.
  • DAfter assigning the confirmed quantity of a material component due to carrying out a material

How the community answered

(44 responses)
  • A
    2% (1)
  • B
    80% (35)
  • C
    7% (3)
  • D
    11% (5)