C_TSCM42_65 · Question #11
In SAP ECC, you calculate the standard available capacity for a work center capacity with the following data: start: 7:00:00 a.m., end. 3:00:00 p.m., break duration: 1 hour, rate of utilization…
The correct answer is C. 5.6 hours. See the full explanation below for the reasoning.
Question
In SAP ECC, you calculate the standard available capacity for a work center capacity with the following data: start: 7:00:00 a.m., end. 3:00:00 p.m., break duration: 1 hour, rate of utilization:
80%, overload. 110%, number of individual capacities: 1. How large is the standard available capacity?
Options
- A7 hours
- B8 hours
- C5.6 hours
- D6.16 hours
How the community answered
(32 responses)- A6% (2)
- B13% (4)
- C78% (25)
- D3% (1)