C_TSCM42_65 · Question #147
Which activities lead to a reduction of the capacity requirements for an operation? (Choose three)
The correct answer is A. Confirming the operation C. Setting the status technically complete (TECO) D. Reducing the order quantity. See the full explanation below for the reasoning.
Question
Which activities lead to a reduction of the capacity requirements for an operation? (Choose three)
Options
- AConfirming the operation
- BRescheduling the operation
- CSetting the status technically complete (TECO)
- DReducing the order quantity
- EPosting the goods receipt for the production order
How the community answered
(27 responses)- A74% (20)
- B7% (2)
- E19% (5)