nerdexam
SAP

C_TSCM42_65 · Question #146

Which of the following activities is necessary for the capacity availability check to be carried out automatically when a production order is released?

The correct answer is A. Activate the availability check and assign an overall profile in checking control for the business function. See the full explanation below for the reasoning.

Question

Which of the following activities is necessary for the capacity availability check to be carried out automatically when a production order is released?

Options

  • AActivate the availability check and assign an overall profile in checking control for the business function
  • BAssign an appropriate availability checking rule to the material master for the product.
  • CActivate the availability check and assign an overall profile in the production scheduling profile.
  • DSet the finite scheduling indicator and assign a checking rule in the work center for the operation to be

How the community answered

(30 responses)
  • A
    73% (22)
  • B
    3% (1)
  • C
    7% (2)
  • D
    17% (5)

Community Discussion

No community discussion yet for this question.

Full C_TSCM42_65 Practice