SAP
C_TSCM42_65 · Question #148
Which of the following efforts can be minimized using the KANBAN procedure?
The correct answer is B. Organizational effort for material staging. See the full explanation below for the reasoning.
Question
Which of the following efforts can be minimized using the KANBAN procedure?
Options
- AEffort for Sales and Operations Planning (SOP)
- BOrganizational effort for material staging
- CEffort for master data maintenance
- DOrganizational effort for capacity planning
How the community answered
(42 responses)- A14% (6)
- B79% (33)
- C5% (2)
- D2% (1)
Community Discussion