C_TSCM42_65 · Question #12

A finished material is to be planned in a controlled manner in the SAP ECC system in the context of requirements planning. The planned orders are scheduled using what is known as basic date…

The correct answer is B. In multi-level backward scheduling, dependent requirements are triggered at the start date for. See the full explanation below for the reasoning.

Question

A finished material is to be planned in a controlled manner in the SAP ECC system in the context of requirements planning. The planned orders are scheduled using what is known as basic date scheduling (not lead-time scheduling). Which of the following statements is true for the resulting dependent requirements?

Options

  • AWhen a customer order is created for the finished product, the dependent requirements are
  • BIn multi-level backward scheduling, dependent requirements are triggered at the start date for
  • CIn multi-level backward scheduling, dependent requirements are triggered at the start date for
  • DIf individual material components are explicitly assigned to operations during BOM and routing

How the community answered

(67 responses)
  • A
    3% (2)
  • B
    76% (51)
  • C
    15% (10)
  • D
    6% (4)