C_TSCM42_65 · Question #73
A supply chain planning run is to be carried out in the SAP ECC system as an example. What would be the most effective sequence in which to run through the planning modules?
The correct answer is B. 1. Sales and Operations Planning. See the full explanation below for the reasoning.
Question
A supply chain planning run is to be carried out in the SAP ECC system as an example. What would be the most effective sequence in which to run through the planning modules?
Options
- A
- Long-term planning
- B
- Sales and Operations Planning
- C
- Capacity planning
- D
- Demand management
How the community answered
(42 responses)- A5% (2)
- B83% (35)
- C10% (4)
- D2% (1)