Which production order function can no longer be carried out after the order is released?
The correct answer is B. Switching sequences. See the full explanation below for the reasoning.
Question
Which production order function can no longer be carried out after the order is released?
Options
- ARead PP master data.
- BSwitching sequences.
- CPosting a goods issue from stock to the production order.
- DPosting a goods receipt from production to stock.
How the community answered
(18 responses)- A6% (1)
- B78% (14)
- C6% (1)
- D11% (2)