Which of the following activities is necessary for the capacity availability check to be carried out automatically when a production order is released?

The correct answer is C. Activate the availability check and assign an overall profile in check control for the business function. See the full explanation below for the reasoning.

Question

Which of the following activities is necessary for the capacity availability check to be carried out automatically when a production order is released?

Options

  • AActivate the availability check and assign a checking rule to the work center for the operation to
  • BActivate the availability check and assign the check control to the plant.
  • CActivate the availability check and assign an overall profile in check control for the business function
  • DActivate the availability check and assign an availability checking group to the material master for

How the community answered

(33 responses)
  • A
    3% (1)
  • B
    15% (5)
  • C
    73% (24)
  • D
    9% (3)