C_TSCM42_65 · Question #85
A project team member analyzes the following situation in SAP ECC in the stock/requirements list for a finished product: there is only one customer order and one fixed planned order with a similar…
The correct answer is C. The time misalignment falls within the tolerance window defined in Customizing. D. The requirement coverage element is outside the rescheduling horizon. See the full explanation below for the reasoning.
Question
A project team member analyzes the following situation in SAP ECC in the stock/requirements list for a finished product: there is only one customer order and one fixed planned order with a similar quantity amount. The customer order and the planned order both have deadlines on work days but not on the same work day; the planned order has a later deadline. The project team member cannot find a rescheduling message referring to this deadline misalignment in the stock/requirements list. What reasons could there be for the missing message? (Choose two.)
Options
- ARequirement planning has not yet been carried out to update the rescheduling message.
- BThe elements are linked to each other via fixed pegging.
- CThe time misalignment falls within the tolerance window defined in Customizing.
- DThe requirement coverage element is outside the rescheduling horizon.
How the community answered
(25 responses)- A4% (1)
- B16% (4)
- C80% (20)