Your customer tests the firming options for planned orders in SAP ECC using a test material. Therefore, the customer sets a firming date in the stock/requirements list manually. Additionally, the…
The correct answer is A. By the firming mechanism that spans further into the future. See the full explanation below for the reasoning.
Question
Your customer tests the firming options for planned orders in SAP ECC using a test material. Therefore, the customer sets a firming date in the stock/requirements list manually. Additionally, the customer sets a planning time fence with firming type 1 in the material master. How is the resulting firming interval specified in this scenario?
Options
- ABy the firming mechanism that spans further into the future.
- BBy the manual firming date.
- CIt is predefined in Customizing.
- DBy the planning time fence from the material master.
How the community answered
(43 responses)- A84% (36)
- B9% (4)
- C5% (2)
- D2% (1)