C_TSCM42_65 · Question #55

What repetitive manufacturing options can you use to carry out line loading in the SAP ECC system and thus generate Run Schedule Quantities (RSQ) from normal planned orders? (Choose three.)

The correct answer is A. Automatic selection of the production version in material requirements planning (MRP) using Selection B. Manual assignment of planned production quantities in a planning table. C. Automatic selection of the production version by applying quota arrangement records in material. See the full explanation below for the reasoning.

Question

What repetitive manufacturing options can you use to carry out line loading in the SAP ECC system and thus generate Run Schedule Quantities (RSQ) from normal planned orders? (Choose three.)

Options

  • AAutomatic selection of the production version in material requirements planning (MRP) using Selection
  • BManual assignment of planned production quantities in a planning table.
  • CAutomatic selection of the production version by applying quota arrangement records in material
  • DUsing a planning algorithm from capacity planning.
  • ESelecting a suitable repetitive manufacturing profile that contains an option for automatic line selection.

How the community answered

(33 responses)
  • A
    70% (23)
  • D
    21% (7)
  • E
    9% (3)