Question
What sequence do you follow in master data maintenance to define the production of a material?
Options
- ACreate BOM -> Create work centers -> Create routing -> Carry out component assignment in BOM or
- BCreate BOM -> Create work centers -> Create routing -> Carry out component assignment in work center
- CCreate routing -> Create work centers -> Create BOM -> Carry out component assignment in BOM or
- DCreate work centers -> Create routing -> Create BOM -> Carry out component assignment in work center