What sequence do you follow in master data maintenance to define the production of a material?

The correct answer is A. Create BOM -> Create work centers -> Create routing -> Carry out component assignment in BOM or. See the full explanation below for the reasoning.

Question

What sequence do you follow in master data maintenance to define the production of a material?

Options

  • ACreate BOM -> Create work centers -> Create routing -> Carry out component assignment in BOM or
  • BCreate BOM -> Create work centers -> Create routing -> Carry out component assignment in work center
  • CCreate routing -> Create work centers -> Create BOM -> Carry out component assignment in BOM or
  • DCreate work centers -> Create routing -> Create BOM -> Carry out component assignment in work center

How the community answered

(62 responses)
  • A
    82% (51)
  • B
    6% (4)
  • C
    2% (1)
  • D
    10% (6)