C_TSCM42_65 · Question #94
What sequence do you follow in master data maintenance to define the production of a material?
The correct answer is A. Create BOM -> Create work centers -> Create routing -> Carry out component assignment in BOM or. See the full explanation below for the reasoning.
Question
What sequence do you follow in master data maintenance to define the production of a material?
Options
- ACreate BOM -> Create work centers -> Create routing -> Carry out component assignment in BOM or
- BCreate BOM -> Create work centers -> Create routing -> Carry out component assignment in work center
- CCreate routing -> Create work centers -> Create BOM -> Carry out component assignment in BOM or
- DCreate work centers -> Create routing -> Create BOM -> Carry out component assignment in work center
How the community answered
(62 responses)- A82% (51)
- B6% (4)
- C2% (1)
- D10% (6)